Back to the specification
The Clothing Consortium / Specification, phase one / November 2026

One UK made T shirt: the specification

An open source supply chain for one UK made T shirt. One published specification that any manufacturer can quote against and any buyer or distributor can order against. The first order is planned for 5,000 units in early 2027.

Download PDF

Contents

  1. 01 The garment
  2. 02 The fabric
  3. 03 Material per T shirt
  4. 04 The route, five stages
  5. 05 Volumes and planning tiers
  6. 08 How to take part
  7. 06 Cost assumptions by stage (manufacturers only)
  8. 07 Cost per T shirt, ex works (manufacturers only)

Online version: theclothingconsortium.co.uk/specification/. Progress is updated regularly on the blog.

Manufacturers only

The cost sections are shared with manufacturers who are quoting for the work. If you are a manufacturer and do not yet have the login, register your capacity or email manufacturing@theclothingconsortium.co.uk.

Section 01

The garment

One adult crew neck T shirt in 200 gsm single jersey. Knitted, dyed, cut, sewn and finished in the United Kingdom, from imported yarn.

Garment, phase one
ItemSpecification
ProductAdult crew neck T shirt
FabricSingle jersey
Finished weight200 gsm
Fibre100% cotton, combed, ring spun
KnittingUnited Kingdom
Dyeing and finishingUnited Kingdom
Cutting and sewingUnited Kingdom
YarnImported in phase one
FitUnisex
Sizes2XS, XS, S, M, L, XL, 2XL, 3XL
ColoursTo be agreed

Why the yarn is imported

UK cotton spinning has gone. Phase one is therefore described exactly as it is: knitted, dyed, cut, sewn and finished in the UK, with imported yarn. Rebuilding spinning in the UK is what sustained volume is for, and it is not claimed here.

Colours

Colours are to be agreed with buyers. White and coloured garments are costed separately, because a white garment is prepared and bleached rather than dyed. Both are shown on the cost per T shirt page, which is shared with manufacturers behind a login.

Sizes and measurements

Eight unisex sizes, from 2XS to 3XL. The size specification below is version 1 and, like the rest of the garment specification, is out for approval and testing.

Size specification, centimetres
CodePoint of measureTolerance minusTolerance plusGrade2XSXSSMLXL2XL3XL
A02Length, side neck point to hem, front11269.571.573.575.577.579.581.583.5
A01Length, side neck point to hem, back11269.571.573.575.577.579.581.583.5
B01Chest at armhole1134750535659626568
C02Waist position from side neck point0.50.513536373839404142
C01Waist, straight across1134548515457606366
E01Hem width, straight11346.549.552.555.558.561.564.567.5
E06Hem depth0002.52.52.52.52.52.52.52.5
A10Twin needle stitch at hem and cuff0.5000.50.50.50.50.50.50.50.5
G04Across shoulder, point to point0.50.524143454749515355
B02Across front, 15 cm from side neck point0.50.523436384042444648
B03Across back, 15 cm from side neck point0.50.5235.537.539.541.543.545.547.549.5
H01Armhole, straight0.50.512223242526272829
G01Sleeve length from top of armhole0.50.521820222426283032
I01Bicep at underarm0.50.511819202122232425
I03Sleeve opening0.50.5116.517.518.519.520.521.522.523.5
I06Cuff depth0002.52.52.52.52.52.52.52.5
J01Back neck width, including rib0.50.50.51717.51818.51919.52020.5
J02Front neck drop, to seam0.50.50.310.110.410.71111.311.611.912.2
J04Back neck drop, to seam0004.54.54.54.54.54.54.54.5
J11Neck trim depth00022222222
J16Minimum neck stretch0003232323232323232

All measurements are in centimetres. Tolerance is how far a finished garment may measure below or above the figure shown. Grade is the step between one size and the next. Size M is the base size from which the others are graded. On a phone, scroll the table sideways to see every size.

Section 02

The fabric

The fabric that every knitter and dyer quotes against. Where a figure is still under review, it says so.

Fabric construction
ParameterValue
Yarn countNe 18/1, combed, ring spun
Cotton100% BCI cotton (Better Cotton)
Machine gauge20 gauge, loose knit (under review)
Stitch lengthApproximately 3.10 mm to 3.30 mm
Finished weight200 gsm
Tolerances
MeasureTolerance
WeightPlus or minus 5%
ShrinkagePlus or minus 5%
Bow and skewPlus or minus 5%
Colour fastness standardTo be confirmed

Why the gauge is under review

The specification currently assumes a 20 gauge machine knitting a loose construction. Many UK knitters run 24 or 28 gauge machines. If a finer gauge can reach 200 gsm finished with the right handle and at the right cost, the specification should change to suit the machines that already exist in the UK, not the other way round.

Knitters: if your machines can meet this fabric on a different gauge, tell us how.

Section 03

Material per T shirt

Worked backwards from the weight of cotton in the finished garment, allowing for the loss at each stage.

Material per T shirt
StageWeight per T shirtLoss assumed before the next stage
Yarn bought0.2524 kg1.5% yarn loss
Greige fabric0.2486 kg4% knit and dye loss
Finished fabric0.2386 kg12% cutting loss
In the garment0.2100 kgNot applicable
Assumed losses
StageLoss
Yarn1.5%
Knitting and dyeing, combined4%
Cutting12%

These weights drive every tonnage on the volumes page and every per kilogram cost on the cost assumptions page. A better loss figure from a working factory improves all of them.

Section 04

The route, five stages

Five stages from yarn to stock. Nobody has to cover all of them. A manufacturer can quote for a single stage.

The route
StageNameWhat happensWhere
01YarnImported and landed in the UKSpun abroad, landed in the UK
02KnitGreige fabric knitted to 200 gsmUnited Kingdom
03DyeDyed and finished in the UKUnited Kingdom
04Cut and sewCut, sewn, pressed, checked and packedUnited Kingdom
05StockHeld by distributors for buyersUnited Kingdom

Why stock is a stage

A garment that is made but not held anywhere does not reach a customer. Between the factory and the buyer sits the party who holds the stock, and that is a trade in its own right. It is part of the route, not an afterthought.

Section 05

Volumes and planning tiers

Four planning tiers. They are not orders. They show what the route has to carry at each level of sustained volume.

Planning tiers
T shirtsYarn, tonnesGreige fabric, tonnesT shirts a week
100,000 a year25.224.9About 1,900
250,000 a year63.162.1About 4,800
500,000 a year126.2124.3About 9,600
1,000,000 a year252.4248.6About 19,200

Planning tiers, not orders. Weekly figures assume 52 weeks. Tonnages use the weights on the material per T shirt page.

The first order

The first order is planned for 5,000 units in early 2027. The tiers show what the route needs once volume is sustained, so that every stage can see what it would be quoting for beyond the first run.

Section 08

How to take part

Three roles make the route work. Each can take part without joining anything and without being named.

Roles
WhoWhat they doRegister
ManufacturersQuote against the specification for any stage: knitting, dyeing and finishing, or cut and sew. You do not need to cover more than one.Register capacity
DistributorsHold stock between the factory and the buyer.Register as a distributor
BuyersCommit forward volume, so that the order is real.Register demand

Nobody has to be named

Manufacturers, distributors and buyers can take part without being named publicly. There is no member list and no fee. A quote, a stock commitment or a forward order is what counts, not a logo on a web page.

What happens next

The first order is planned for 5,000 units in early 2027. Progress is updated regularly on the blog.